Compare quotations against one accepted finished part at the same drawing revision. Kilogram and metre prices help check stock material, but do not establish the delivered price after holes, bends, insulation and inspection. A copper replacement must also meet agreed functional requirements before its cost is compared.

01

Define the deliverable before converting prices

Identify the drawing, revision, Cu-Al layer arrangement and delivery state. Quote straight stock, machined bare conductors and insulated assemblies separately. ISO 7200 addresses identification fields in technical documents; layer dimensions and acceptance requirements still belong in the project specification.

For an ESS PCS replacement, review mating interfaces, available space and electrical and thermal validation. Similar weight does not establish equivalent function when cross-sections or layer arrangements differ.

02

Use mass per metre only for the matching stock

For uniform straight stock, mass per metre multiplied by length gives the segment mass. Apply the agreed price per kilogram to estimate that material amount. All inputs must describe the same construction and supply state. Holes, local machining or added fittings require finished net mass and chargeable mass to be distinguished.

Ask whether settlement uses measured or theoretical mass, and how offcuts, punched waste and cutting loss are charged. Adding a loss allowance already included in the material charge counts it twice.

03

Separate recurring work from one-time charges

Compare material, processing, finish, insulation, assembly, inspection and packaging. List tools and dedicated gauges separately, including ownership, amortization quantity and repeat-order terms. Align tax, transport and quotation validity.

Request prototype, first-batch and production prices separately. Annual forecasts are not committed orders. Compare the same purchase quantity before evaluating assembly or validation cost changes, without assuming a universal saving percentage.

04

Frequently asked questions

Can a higher kilogram price still give a lower piece cost? Only a calculation using actual mass, consumption and the same delivery scope can answer that question.

Can theoretical mass be used for settlement? Agree the method and its applicable specification and delivery state with the supplier first.

05

Comparison and RFQ inputs

Provide PCS busbar drawings, layer construction, insulation coverage and batch quantity. Request stock chargeable mass, finished net mass, processing scope and one-time charges separately. For a copper replacement, list resistance, temperature-rise, connection and space requirements needing validation. Product, application and drawing-RFQ links follow.

Apply this guide to a project

Use product pages to identify the hardware family and the calculator for early estimates only. Acceptance depends on drawings, operating conditions and project tests.

Sources

  1. ISO 7200 technical-document data fields↗
  2. Related application and hardware selection↗
  3. Send drawings and operating conditions for RFQ↗